Resources on unit TODAY

Resource Committed Available
Engines: 2  
Crews: 1  
Firefighters:    
Helicopters:    
Dozers:    
Other:    

Today's Fire Manager: Mason
Comments:  

Planned Rx Burning

Project Name Unit Number Est. Date of Ignition Est. Time of Ignition Planned Acres Tons of Fuel per Acre County Legal Descriptive Location Burn Boss Type Comments Updated
Pleasant Fry 900 2/12/11 08:00 35 40 Jackson 34-4W-9 Jamison Gulch Engleson Piles 20 AC COMPLETED 12/12 AND 15AC COMPLETED 12/13 9-May-2012 15:26:12
Flounce 170     53 Total 8 Jackson 33S-2E-17 Lost creek Lake   Piles   6-Nov-2011 14:51:03
Flounce 171     23 Total 3 Jackson 33S-2E-17 Lost Creek Lake   Piles   6-Nov-2011 14:47
Shady Cove 23-4         Jackson       Piles   7-Dec-2011 15:39:42
test           Jackson       Piles   7-Nov-2011 16:19:48
Shady Cove 9-4 1/10/2012 1000 5 9 Jackson T34S R1W Sec. 9 Sawyer Road Mason Piles   10-Jan-2012 15:12:47
Sawyer Road   1/10/2012 0800 5   Jackson 34S R1 Sec9 Sawyer Road in Shady Cove Mason Piles Tons Not included in email. 10-Jan-2012 15:12:57

Completed Rx Burning

Project Name Unit Number Est. Date of Ignition Est. Time of Ignition Planned Acres Tons of Fuel per Acre County Legal Descriptive Location Burn Boss Type Comments Updated
Homerun (Full Service) 31-1 9/28/2010 1200 25 100 Jackson T35S R4W Sec. 31 4 miles NW of Rogue River Greyback Underburn Buchanan will be the agency person on site. 9/26 30ac burned 9/27 20ac burned 10 ac burned on 9/28 28-Sep-2010 17:18:56
Flounce 127 09/29/2010 1100 70 500 Jackson T33S R1E Sec. 12 Lost Creek Lake area Mason Underburn Other=water tenders Bob Rathjen is doing Burn boss Trainee on this burn all week. Burned 100acres on 9/28/10 Burned 66ac on 9/29/10 this completes the unit 29-Sep-2010 15:47:32
Collins PVT   2/9/11 0800 3 5 Jackson T35S R3W sec 33 3 miles NW of Gold Hill Engleson Piles Small inhouse burn completed 22ac on 11/30 finishing 3 acres 3ac completed2/9/11 9-Feb-2011 14:13:46
Pleasant Fry 320 11/18/11 08:00 40 45 Jackson 34S-4W-32 Dixie Gulch Engleson Piles Added to the plann today to replace BF HWY. 21-Nov-2011 8:47:407
Pleasant Fry 700 11/9/2011 0700 44 376 Jackson 35S-4W-7 Queens Branch Rd   Piles   7-Dec-2011 15:44:32
Lysinger PVT   2/9/11 0800 3 5 Jackson 35-3W-33 Sardine Cr Engleson Piles Private Land 7 Basins Funded Unit has been completed 3ac 2/9/11 9-Feb-2011 11:56:54
Bear Head 10 12/29/2011 0900 14 7 Jackson 35-5W-25 Granite Hill Rd Mason Piles   29-Dec-2011 15:14:53
Shady cove 23-2   2/8/11 0800 1 15 Jackson 34-1W-23 Indian Creek in Shady cove Engleson Piles Clean up of pile rings 7-Feb-2011 14:50:45
Fred and Jack 35-3 10/27/2011 1300 16 97 Jackson T34-2E-35 Fredenburg Engleson Underburn 16 acres completed on 10/27/11 27-Oct-2011 16:00:52
Fred and Jack 35-5 10-21-11 1000 52 270 Jackson T34S R2E Sec 35 Fredenburn Road Buchanan Underburn Completed Unit 10-21-11 21-Oct-2011 16:25:42
Fielder 507 10/28/11 1100 59 3 Jackson T36S R4W sec 5 2 miles North of Rogue River Leo Engelson & Trevor Wallace Trainee Underburn This burn is highly visible from I-5 and the town of Rogue River Competed 59 ac on 10/28/11 28-Oct-2011 15:50:54
Battle Mtn 14-1 11/08/2011 0900 35 7 Jackson 34S-4W-14 Pleasant Cr Buchanan Piles Completed the unit on 11/8/11 8-Nov-2011 12:08:11
Bear Fielder 25-1 12/29/2011 0900 28 8 Jackson 35S-5W-25 Bear Branch Mason Piles Completed 28 ac on 12/29/11 4-Jan-2012 8:05:4836
Shady Cove 23-1 11/09/2011 0900 60 6 Jackson 34S-1W-23 Indian Cr Buchanan Piles Unit completed 11-9-11 9-Nov-2011 13:38:22
Bear Fielder 31-1 11/17/11 0900 21 7 Jackson 35S-4W-31 Fielder Cr Engleson Piles   17-Nov-2011 15:20:31
Shady Cove 23-4 11/8/11 0800 30 10 Jackson 34S-1W-23 Indian Cr Engleson PI Piles Completed 11-8-11 8-Nov-2011 14:39:45
Home Run 28-1 11/08/2011 0800 19 7 Jackson T35S-R4W-sec 28 Evans Crk Buchanan Piles completed the 19ac on 11/08/11 8-Nov-2011 15:57:43
Flounce 170 and 171 11/09/2011 0800 11 7 Jackson T33S R2E Section 17 Lost Creek Lake Engleson Piles Completed unit 11-9-11 9-Nov-2011 13:29:04
Shady Cove 23-3 11/09/2011 1100 150 7 Jackson T34S R1W Section 23 Indian Creek Buchanan Piles Completed unit 11-9-11 9-Nov-2011 13:39:52
East Evans Creek 270 11/09/2011 0900 60 8 Jackson T34S R2W Section 27 Antioch Road Engleson Piles Completed unit 11-9-11 9-Nov-2011 13:41:14
Cardwell Creek 27-4 11/17/2011 1000 43 7 Jackson T35S R3W Section 27 Sardine Buchanan Piles   17-Nov-2011 16:06:49
Pleasant Creek 700 11/10/2011 1100 44 7 Jackson T34S R4W Section 7 Queens Creek Engleson Piles   9-Nov-2011 15:44:43
Butte Falls Hwy 7-2 11/21/2011 0900 5 4 Jackson 35S R1E Sec 7 Butte Falls Highway Engleson Piles 21-Nov-2011 16:12:47
Flounce 900 1/20/12 0900 35 16 Jackson 33S-2E-9 Lost Cr lake Engleson Piles   20-Jan-2012 16:03:09
Right Fork Sardine Creek 29-4 1/30/2012 1000 1 4 Jackson T35S-R3W-29 4 miles NE of Rogue River Engleson Piles 1 acre completed in Sit Report 1/30/12 30-Jan-2012 15:58:52
Right Fork Sardine Creek 29-5 1/21/2012 0800 14 7 Jackson T35S-R3W-29 4 miles NE of Rogue River Engleson Piles   23-Jan-2012 7:01:067
Old Ferry 10-1 1/302012 1000 1 4 Jackson 34-1W-10 Shady Cove Mason Piles 4 acres completed and will go back next season 30-Jan-2012 15:58:08
Pleasant Fry 901 05-10-2012 1100 63 4 Jackson 34S-4W-9 Pleasant Fry Grayback Underburn Full Service 10-May-2012 16:49:43
Butte Falls Hwy 7-1 5/10/12 1000 93 4 Jackson 35S-1E-7 Butte Falls Highway Mason Broadcast Smoke may be visible from Medford. Unit borders the main Butte Falls Highway 10-May-2012 16:01:29
Lower Down 16 5/12/12 0900 44 7 Jackson 34S 2E 16 Cobleigh Road Jessica Gallimore Underburn Completed 44 acres 5/11/12, Unit Completed 5/12/12 12-May-2012 14:21:22
Lookout Below 31.3 5/11/12 1000 50 8 Jackson 34S 3E 31 Butte Falls Prospect Hwy Al Mason Underburn Completed 5/11/12 11-May-2012 16:00:34

[MICC Prescribed Burning]